Project Location
The St. Columban Wind Facility is located approximately 60 km north of London, Ontario in Huron County.
Additional Resources
Regulatory Approvals and Documents
This facility is classified as a Class 4 Wind Facility and received a Renewable Energy Approval (REA) in accordance with Ontario Regulation 359/09 from the Ontario Ministry of the Environment on July 2, 2013. An amendment to the REA was approved on July 11, 2016. All related documents are located below.
- Project Description Report
- Consultation Report
- Construction Plan Report
- Design and Operations Report
- Project Design Change Addendum Information Package (Oct. 2012)
- REA Amendment Approval
- Renewable Energy Approval
- Decommissioning Plan Report
- Heritage Impact Assessment Report and Confirmation Letter
- Stage 1 Archaeological Report – Wind Study Area
- Stage 1 Archaeological Report – Wind Study Area Confirmation Letter
- Stage 2 Archaeological Report – Wind Study Area
- Stage 2 Archaeological Report – Wind Study Area Confirmation Letter
- Stage 1 and Stage 2 Archaeological Report – Interconnection Line Study Area
- Stage 1 and Stage 2 Archaeological Report – Interconnection Line Study Area Confirmation
- Natural Heritage Assessment and Environmental Impact Study Report and Wind Study Area Confirmation Letter
- Natural Heritage Assessment and Environmental Impact Study — Interconnection Line Study Area (and Confirmation Letter)
- Water Assessment and Water Body Report
- Wind Turbine Specifications Report
- Spring Acoustic Audit Immission Report
- Fall Acoustic Audit Immission Report
Community Consultation
The St. Columban Wind Facility established a Community Liaison Committee to provide a forum for information sharing and discussion during construction. The committee facilitated two-way communication between the project team and stakeholders.
The last meeting was held on May 16, 2016.
- Notice of Draft Site Plan and a Proposal to Engage in Renewable Energy Project
- Notice of Application – Ontario Board of Energy
- Notice of Open House on May 26, 2011
- Open House Information Boards (May 2012)
- Open House Display Board (January 2012)
- Stakeholder Questions & Project Responses (August 2011)
- SCELP Community Liaison Committee Meeting Minutes (May 16, 2016)
- Notice of SCELP Community Liaison Committee Meeting (May 16, 2016)
- SCELP Community Liaison Committee Meeting Minutes (November 18, 2015)
- Notice of SCELP Community Liaison Committee Meeting (November 18, 2015)
- SCELP Community Liaison Committee Agenda (November 18, 2015)