  • Stage:

    Construction

  • Capacity:

    54 MW

  • Power Sales:

    Long-term PPA with Independent Electricity System Operator

Project Location

The Loyalist Solar Project is located in the Township of Stone Mills, Lennox & Addington County, Ontario.

Project Schedule

  • Permitting: 2015 – Q1 2018
  • Construction Start: March 2018
  • Block A Major Construction: April 2018 – Sept 2018
  • Block B Major Construction: May 2018 – Sept 2018
  • Block D Major Construction: June 2018 – Oct 2018
  • Block C Major Construction: July 2018 – Oct 2018
  • Connection Line Major Construction: May 2018 – November 2018
  • Commencement of Operation: January 2019 (Anticipated)

About Our Partnership

The Mohawks of the Bay of Quinte are a full commercial partner with BluEarth Renewables in the Loyalist Solar Facility. Together, we formed Loyalist Solar LP and both parties share in the economic benefits, risks and costs of the joint venture.

We are proud to partner with the Mohawks of the Bay of Quinte, and we work closely with the Nation to provide ongoing, long-term economic benefits to the region.

Learn more about our approach to working with Indigenous Peoples.

Additional Resources

Renewable Energy Approvals & Project Documents

The Project is classified as a Class 3 Solar Facility and requires a Renewable Energy Approval (REA) from the Ontario Ministry of the Environment and Climate Change (MOECC) in accordance with Ontario Regulation 359/09 (“O. Reg. 359/09”). A copy of the notice, supporting documentation and REA reports are posted below. For efficiency, we recommend downloading the documents.

Stage 1 & 2 Archaeological Assessment
Cultural Heritage Assessment
Noise Study Report
Natural Heritage Assessment Reports
Water Body & Water Assessment Reports
Consultation Report
Public Meetings
Project Newsletters
Public Notices
Stormwater Management and Erosion & Sediment Control Plans