In case of emergency, please call 1-877-359-0671

  • Stage:

    Operating

  • Technology:

    36 – 1.62 MW wind turbines

  • Capacity:

    58.32 MW

  • Commercial Operation Date:

    2015

  • Power Sales:

    Long-term PPA with Independent Electricity System Operator

Project Location

The Bow Lake Wind Facility is located in Algoma district, close to the eastern edge of Lake Superior and south of the Montreal River in an area that has been, and continues to be, used for hydroelectric generation, mining and forestry.

Bow Lake Wind Project

Play Now

About Our Partnership

In September 2024, the Batchewana First Nation acquired 100% ownership of the Bow Lake Wind Facility, and BluEarth continues to oversee the operations and maintenance. The Facility first achieved commercial operations in 2015, and at the time of commissioning set the precedent as one of the largest economic partnerships between a First Nation and a wind energy developer in Canada.

Learn more about our approach to working with Indigenous Peoples.

Additional Resources
Acoustic Audit
Consultation Report
Amendment Modification Report
Additional Reports
Renewable Energy Approval
Archeological and Heritage Resources, Tourism
Natural Heritage Assessment
Water Assessment and Water Body Report
Public Consultation
Project Newsletters
Ministry of Natural Resources APRD
Disposition of Crown Land

Ministry of Natural Resources (MNR) permits have been obtained during the development phase of the Project for investigative activities such as the installation of meteorological towers, and the undertaking of geotechnical investigations.

The Project will use, to the extent possible, public multi-use roads that have been approved under the Forest Management Planning (FMP) process to reduce the number of new roads required for construction. The FMP roads include existing multi-use roads and approved road locations that have yet to be constructed. Accordingly, approval for these roads have been obtained as part of the forest operator’s approved annual work schedule as part of their Sustainable Forest Management Plan.

As the Project is located predominantly on Crown land, it will require authorization from MNR for disposition of Crown land and to complete the construction work on Crown land. During the construction and operation phases, the Project will obtain all work permits, land use permits, leases, licences of occupation, and easements as required by MNR.

Community Liaison Committee